Employer
INITIATIVE MILOS S.A.
Contractor
MESOGEOS SA
Capacity
2.500 pe
Duration
03/2008-05/10
Budget
686.000 € construction + 36.000 € 3-month trial operation + 156.000 € 2-year operation
The project involves the construction of a Wastewater Treatment Plant to serve the needs of the Municipalities of the area. The treatment steps of the plant are:
1)Reception and sewage pretreatment. 2)Biological treatmet in MBR unit with simultaneous nutrients removal. 3)Sludge treament including mechanical thickening-dewatering. 4) Disinfection of the produced sludge before disposal for irrigation in adjacent sites.