Contracting Authority
Attica Region
Contractor
LAMDA TECHNIKI-HELECTOR-MESOGEOS S.A.
Capacity
2.000.000 m3
Budget
20.925.454,66 €
Contract Duration
05/2008-………….
The project concerns the design, built, procurement and execution of all required works for the complete construction of Phase A of the landfill and includes the following:
- Excavation works
- Sealing works
- Leachate management works (collection- treatment – disposal)
- Biogas management works (collection – disposal)
- Stormwater runoff and drainage works
- Internal road works
- Building works and landscaping
- Environmental monitoring and Surveillance (Gas and Groundwater Monitoring, Remote Monitoring Network)
- Three month trial operation of the project
- Professional training of the personnel who will operate the project
- Access road
The Leachate Treatment Plant is composed of the following sections:
- Inlet / Screen Pit
- Pumping station – Equalization tank
- Primary settling tank
- Biological treatment tank
- Settling tank/ R.A.S. pump
- Thickening – temporary storage tank
- R.O. feeding tank
- R.O.
- Disinfection tank / recirculation pump.